Ready to report tasks seem to just sit there

Questions and Answers : Wish list : Ready to report tasks seem to just sit there

To post messages, you must log in.

AuthorMessage
Robert Bethman

Send message
Joined: 6 Jan 12
Posts: 6
Credit: 118,039
RAC: 0
United States
Message 1315649 - Posted: 15 Dec 2012, 17:50:06 UTC

Is there some "magic" incantation or command that can make BOINC send the stack of "Ready to Report" items?

The seem to sit there, and there is no apparent way to get them sent.
ID: 1315649 · Report as offensive
Profile Ageless
Avatar

Send message
Joined: 9 Jun 99
Posts: 13822
Credit: 3,269,733
RAC: 0
Netherlands
Message 1315704 - Posted: 15 Dec 2012, 19:35:08 UTC - in response to Message 1315649.  

BOINC will do this automatically in 24 hours, but if you can't wait that long, open BOINC Manager, Advanced view, Projects tab, select the project the task is from and press the Update button. That reports the tasks that are ready to report immediately.

Completed work is reported at the first of:

1) 24 hours before deadline.
2) Connect Every X before deadline.
3) 24 hours after task completion.
4) Immediately if the upload completes later than either 1, 2, or 3 upon completion of the task.
5) On a trickle up message.
6) On a trickle down request.
7) On a server scheduled connection. Used, but I am not certain by which project.
8) On a request for new work.
9) When the user pushes the update button.
10) On a request from an account manager.
11) Report immediately every task, if "No new Task" is set.
12) Report immediately if CPU or network time-of-day override starts in the next 30 minutes. (BOINC 7.0)
13) When minimum work buffer is reached. (BOINC 7.0)
Jord

Ancient Astronaut Theorists suggest that in many ways, you can be considered an alien conspiracy!
ID: 1315704 · Report as offensive
John McLeod VII
Volunteer developer
Volunteer tester
Avatar

Send message
Joined: 15 Jul 99
Posts: 24806
Credit: 754,585
RAC: 65
United States
Message 1315706 - Posted: 15 Dec 2012, 19:37:56 UTC - in response to Message 1315704.  

BOINC will do this automatically in 24 hours, but if you can't wait that long, open BOINC Manager, Advanced view, Projects tab, select the project the task is from and press the Update button. That reports the tasks that are ready to report immediately.

Completed work is reported at the first of:

1) 24 hours before deadline.
2) Connect Every X before deadline.
3) 24 hours after task completion.
4) Immediately if the upload completes later than either 1, 2, or 3 upon completion of the task.
5) On a trickle up message.
6) On a trickle down request.
7) On a server scheduled connection. Used, but I am not certain by which project.
8) On a request for new work.
9) When the user pushes the update button.
10) On a request from an account manager.
11) Report immediately every task, if "No new Task" is set.
12) Report immediately if CPU or network time-of-day override starts in the next 30 minutes. (BOINC 7.0)
13) When minimum work buffer is reached. (BOINC 7.0)

#13 and #8 are the same.


BOINC WIKI
ID: 1315706 · Report as offensive
Robert Bethman

Send message
Joined: 6 Jan 12
Posts: 6
Credit: 118,039
RAC: 0
United States
Message 1316087 - Posted: 16 Dec 2012, 16:22:26 UTC - in response to Message 1315704.  

I discovered the "Update" by accident.

Thanks for the response!
ID: 1316087 · Report as offensive